DL/T5235-2010±800kV及以下直流架空输电线路工程施工及验收规范(英文版)

住房和城乡建设部

更新时间:2020-09-25 11:19:40

最新章节:10.4 Project Transfer After Completion
完结共30章
倒序

封面

版权信息

Foreword

1 Scope

2 Normative References

3 Inspection of Raw Material and Equipment

4 Survey

5 Earthwork

APP免费

6 Foundation

APP免费

6.1 General Provisions

APP免费

6.2 Cast-in-site(CIS)Foundation

APP免费

6.3 Cast-in-drilled-hole(CIDH)Pile Foundation

APP免费

6.4 Rock Foundation

APP免费

6.5 Winter Construction

APP免费

7 Tower

APP免费

7.1 General Provisions

APP免费

7.2 Steel Towers

APP免费

8 Installation of Overhead Conductors and Ground Wires

APP免费

8.1 General Provisions

APP免费

8.2 Tension Stringing

APP免费

8.3 Connection

APP免费

8.4 Wire Tightening

APP免费

8.5 Installation of Accessories

APP免费

8.6 Installation of Optical Fiber Composite Overhead Ground Wires(OPGW)

APP免费

9 Grounding

APP免费

10 Acceptance and Transfer

APP免费

10.1 Acceptance

APP免费

10.2 Test on Completion

APP免费

10.3 Transfer of Documents

APP免费

10.4 Project Transfer After Completion

更新时间:2020-09-25 11:19:40

APP免费